FG Don Extend The Reopening Of Third Mainland Bridge

Dem no go open the Lagos Third Mainland Bridge on Monday, February 15,  Federal government don reveal.

The Federal Controller of Works for Lagos, Mr Olukayode Popoola yarn this to tori people say the bridge dem go still shut down again from Feb. 19 to 21 to complete  the project.

Make Una read wetin im yarn


Third Mainland Bridge will no longer be opened on the 15th of February 2021 as announced earlier.

“This decision was taken in order not to create hardship for the motoring public using the Third Mainland Bridge for their daily activities.

“We are looking at the end of the month for the reopening of the bridge. That is, end of this February.

“They will cast concrete on the last expansion joint next weekend and this cannot be done during the week because we are trying to endure that there will not be so much traffic for people going about their daily activities.

“When this casting is done, we need about three or four days to do post tensioning. That is why we are looking at end of February completion.

“Casting will be done next weekend for the last expansion joint and this will require total closure of the bridge.

“However, if we close the bridge Friday night, then we cast on Saturday by Sunday it will be reopened. That will be the last total closure to fix the last expansion joint.

“We also regret the inconveniences these extra days will cause Lagosians,’